skip to main content

Lovett Mechanical installed plumbing throughout the entire 2nd floor of Community Hospital through 5 phases. Our team provided all necessary labor, material, and equipment to complete the renovation of the 2nd floor East and West wings of the Maternity and Nursery units within the location.

Lovett Mechanical provided all necessary labor, material, and equipment in order to complete the renovation of the 2nd and 5th floor Maternity and Operating Room Suites.

Lovett Mechanical plumbing work included the installation of sanitary waste and vent piping, domestic water piping, and valves and fittings that were tied into existing systems.